    Rising to a tunnel's challenge

    By China Daily | China Daily | Updated: 2017-06-09 07:32
    Share
    Share - WeChat

    Workers deal with gushing water during the construction of the Dazhushan Tunnel on the Dali-Ruili Railway project in May.Provided To China Daily

    When work began on the Dazhushan Tunnel, the plan was to finish it in five years. That was in 2008 - and construction crews are still digging.

    Unexpected difficulties mean the 14.5-kilometer tunnel, a critical juncture on the Dali-Ruili Railway in Yunnan province, is now scheduled for completion in 2021, Xinhua News Agency reported.

    The tunnel runs through six faults in the Hengduan Mountains on the Qinghai-Tibet Plateau. It would have been beyond imagination to build on the earth fractures 20 years ago, said You Hongsheng, a spokesman for No 4 Company of China Railway First Group Co, which is digging the tunnel.

    In August 2009, immediately after the first drilling began at one of the six fault lines, a 20-centimeter crack appeared in the operating face. The crack continued to widen as mudrock gushed out, filling a space 200 meters long and 6 meters high in about five hours.

    "We failed to predict the fragility of the fault," said Jiang Dong, a construction manager at the site. "It is just like drilling into a piece of bean curd. The mudrock started to flow into the tunnel as we worked."

    Jiang said the problem was later solved by building a wall to stop the mudrock flow and grouting the flow until it became solid. "Then we dug through the solid part to carry on with the project."

     

    An estimated 140 million cubic meters of water have been pumped out of the tunnel over the past nine years of construction work.

    In addition to the day-to-day operating challenges, the geologic complexity of the area where the tunnel is located has made working conditions extremely tough for workers.

    In most parts of the construction site, it's quite humid, with the temperature in the hole at around 37 C. Workers had to alternate in two-hour shifts to continue through the day.

    Some workers have left the project because of the rough working conditions and the extended construction time. Others, however, stayed put and were determined to hold their ground until the tunnel's completion.

    Jiang said when he began working at the site his daughter was in second grade, and now she is in senior high school. He has been able to be home for just 20 days every year.

    Wu Hao, 25, chose to stay with the project even though his father needed him in the family business.

    "I need to prove myself in this project. How can I give up halfway?" Wu said.

    When the Dali-Ruili Railway is complete, it will take a train just five minutes to run through the tunnel. Few passengers will know that it took 13 years to build.

     

    Top
    BACK TO THE TOP
    English
    Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
    License for publishing multimedia online 0108263

    Registration Number: 130349
    FOLLOW US
     
    亚洲AV无码国产精品色午友在线| 亚洲一级Av无码毛片久久精品 | 无码av免费毛片一区二区| 国产日韩AV免费无码一区二区三区| 久久中文字幕视频、最近更新| 精品无人区无码乱码大片国产| 中文字幕乱偷无码AV先锋| 无码精品视频一区二区三区 | 中文字幕人妻无码专区| 最近2019中文字幕免费直播| 无码精品人妻一区二区三区免费| 亚洲av无码不卡| 亚洲国产一二三精品无码| 人妻丰满熟妇aⅴ无码| 精品久久久久中文字幕日本 | 最近中文字幕免费mv在线视频| 天堂无码久久综合东京热| 99久久无码一区人妻| 精品久久久久久无码专区不卡| 亚洲国产精品无码专区在线观看| 少妇无码太爽了在线播放| 中文字幕不卡亚洲| 国产中文在线亚洲精品官网| 久久精品人妻中文系列| 中文字幕无码一区二区三区本日| 精品人体无码一区二区三区| 波多野42部无码喷潮在线| 国产亚洲AV无码AV男人的天堂 | 67194成l人在线观看线路无码| 无码精品一区二区三区在线 | 久久精品无码一区二区app| 本免费AV无码专区一区| 国产亚洲美日韩AV中文字幕无码成人| 人妻无码αv中文字幕久久琪琪布 人妻无码第一区二区三区 | 无码精品一区二区三区在线| 无码国产色欲XXXX视频| 精品无码无人网站免费视频| 欧洲人妻丰满av无码久久不卡| 东京热加勒比无码视频| 无码 免费 国产在线观看91 | 亚洲日韩中文字幕日韩在线|