    State Grid Corp asks Brazil to speed up power line approval

    China Daily | Updated: 2017-01-05 09:24

    State Grid Corp of China has asked the Brazilian government and regulators to speed up environmental licensing of a planned power line connecting to the Belo Monte dam in the Amazon forest, according to official documents and a source with direct knowledge of the matter.

    State Grid, the world's biggest utility, fears it could have to delay construction of the line, possibly forcing the third-largest hydroelectric power dam to begin operating in 2019 below full capacity.

    Belo Monte, a dam built on the Xingu River in the Amazon forest, will have a total installed capacity of 11,233 megawatts, exceeded only by China's Three Gorges and Brazil's Itaipu dams.

    The Chinese firm, together with two units of the Centrais Elétricas do Brasil SA state-controlled utility, has begun work in the first of two transmission lines linking Belo Monte to cities throughout Brazil.

    The source said State Grid had expected to receive a preliminary license from Brazil's Ibama environmental agency for a second 2,500 kilometers-long transmission line by October 2016 and authorization to begin construction by February 2017.

    Ibama has not issued either of the licenses for the second transmission line, which will carry power to the southeast, Brazil's biggest energy consumer, and other states.

    The source said that while the delay did not affect the construction schedule, the preliminary authorization needs to be issued in January, followed by the building authorization in March.

    Ibama said its analysis was still underway and it had no estimate of when it would be completed.

    Last week, Brazil's power regulator Aneel contacted the Energy and Mining Ministry to ask for support in speeding up the licensing process, an Aneel document seen by Reuters showed.

    Construction of the power line, which State Grid estimates will cost 7 billion reais ($2.15 billion), needs to be completed by December 2019 if Belo Monte is to operate in full capacity.

    A State Grid document seen by Reuters said that delays in the licensing process would also force it to disburse additional money as it could miss deadlines for receiving funds from state development bank BNDES.

    Reuters

    Most Viewed in 24 Hours
    Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
    License for publishing multimedia online 0108263

    Registration Number: 130349
    FOLLOW US
    久久久久亚洲AV无码专区体验 | 久久亚洲中文字幕精品一区| 亚洲国产午夜中文字幕精品黄网站 | 中文成人无码精品久久久不卡| 中文字幕一区二区三区永久| 狠狠躁天天躁中文字幕无码| 精品少妇无码AV无码专区| 中文字幕在线免费看线人| 国产精品无码素人福利| 成人无码A区在线观看视频| 中文字幕人成人乱码亚洲电影| 精品无码国产一区二区三区AV| 中文字幕乱码免费看电影| 欧美日韩久久中文字幕 | 久久无码精品一区二区三区| 亚洲国产一二三精品无码| 亚洲欧美中文字幕| 亚洲熟妇少妇任你躁在线观看无码| 国产成人无码一区二区三区| 中文字幕无码无码专区| 久久久网中文字幕| 日韩欧美中文在线| 亚洲乱码中文字幕久久孕妇黑人| 精品久久久久久无码专区不卡| 亚洲精品无码鲁网中文电影| 久久亚洲日韩看片无码| 亚洲AV中文无码乱人伦| 精品人妻中文字幕有码在线| 中文字幕7777| 国产精品中文久久久久久久| 无码精品前田一区二区| 国产精品热久久无码av| 国产精品无码无卡在线播放| 久久久久久无码Av成人影院| 精品视频无码一区二区三区| 97碰碰碰人妻视频无码| 国产成人精品无码一区二区| 国产成人AV片无码免费| AV成人午夜无码一区二区| 成 人无码在线视频高清不卡| 6080YYY午夜理论片中无码|