Three Gorges project running well

    (Xinhua)
    Updated: 2007-06-30 22:03

    Chinese auditors said it found no embezzlement or misappropriation of construction fund in the ongoing Three Gorges project, however, they also detected some problems and flaws in the project management.

    The National Audit Office (NAO) said the overall quality control of the project was fine and total investment were kept under control.

    All 11 major projects were up to the standards, as were main materials such as steel and cement, said an audit report by the NAO.

    It said total inflation-adjusted investment, expected to be 78 billion yuan, could be more than 35 billion yuan less than planned in 1994. By the end of 2005, the country had spent 64.2 billion yuan on the project.

    The NAO, however, also detected extra construction costs of 488 million yuan, most of which was incurred by project construction contractors who exaggerated their expenditure.

    The office also found 20.4 hectares of land illegally used without governmental permission, while another 110 hectares approved for use had been left idle.

    "The problems are largely due to lack of laws and regulations and imperfection in internal control," said Pan Xiaojun, senior official with the NAO.

    The company said it had already corrected the use of 139 million yuan of fund involving violation of rules, and a total 17 measures had been adopted to improve management over the project.

    The office said 21 power station construction projects, most of which involved a single contract value of less than 10 million yuan were not put out to tender.

    A few construction companies were discovered to have subcontracted their projects against regulations and obtained illegal charge of 53.45 million yuan.

    About half of the 1,448 supervisors sampled were found to have no licenses for the work.

    The China Three Gorges Corporation said it had strengthened the implementation of public bidding to ensure the fairness of the results and avoid the influence of people, and it also added detailed terms about contracting in contracts to prevent illegal contracting.

    The unlicensed supervisors had been fired and supervision over the project supervisors were enhanced, according to the company.

    The report said that the project across the Yangtze River, the construction of which began in 1993, had played a "better-than-expected" role in flood prevention, power generation and shipping.

    "It's possible to put the project into full operation by 2009 as planned, and the project is running a bit ahead of schedule," it said.

    The fourteen generators in a power plant had been put into operation a year earlier than planned in 2005, the office said.

    Upon its completion, the Three Gorges dam will produce 85 billion kwh of electricity annually for supply to central and eastern China.

    The dam, which is 2,309 meters long and 185 meters high, will be installed with 26 turbo-generators, each with a generation capacity of 700,000 kilowatts.

    The audit, which took 150 auditors more than six months to complete, covered areas including fund raising, management and use, construction management as well as benefit of the project.



    Top China News  
    Today's Top News  
    Most Commented/Read Stories in 48 Hours
    中文字幕无码第1页| 日韩精品无码一区二区三区四区 | 亚洲综合无码AV一区二区| 久久影院午夜理论片无码| 在线精品无码字幕无码AV| 无码精品日韩中文字幕| 免费无码午夜福利片69| 熟妇人妻AV无码一区二区三区| 天堂а√在线中文在线| 久久久久亚洲?V成人无码| 日韩精品无码一区二区三区不卡| 无码国产精品一区二区免费式影视 | 最近中文国语字幕在线播放| a级毛片无码兔费真人久久| 国产在线无码精品电影网| 亚洲欧美中文日韩在线v日本| 久久亚洲av无码精品浪潮| 国内精品人妻无码久久久影院| 狠狠躁天天躁中文字幕无码 | 最新中文字幕av无码专区| 久久e热在这里只有国产中文精品99| 无码日韩人妻AV一区免费l | 制服丝袜中文字幕在线| 亚洲国产精品成人AV无码久久综合影院 | 中文字幕丰满乱孑伦无码专区 | 亚洲爆乳精品无码一区二区| 人妻少妇精品无码专区动漫| av无码一区二区三区| 狠狠躁狠狠躁东京热无码专区| 精品久久无码中文字幕| 免费无码毛片一区二区APP| 人妻夜夜添夜夜无码AV| 国产乱子伦精品无码码专区| 人妻aⅴ无码一区二区三区| 韩国免费a级作爱片无码| 成年无码av片在线| 亚洲国产综合无码一区二区二三区 | 免费A级毛片无码A∨免费| 亚洲欧洲美洲无码精品VA| 无码人妻精品一区二区在线视频 | 精品无码三级在线观看视频 |