    Construction of Olympic projects progresses smoothly
    (BOCOG)
    Updated: 2006-12-07 15:36

     

    Continuous progress has been made in the construction of competition venues, training venues and auxiliary facilities for the Beijing 2008 Olympic Games, according to a regular press briefing held in Beijing on Thursday.

    Wu Jingjun, chief engineer of the Beijing 2008 Olympic Project Construction Headquarters Office said safety and quality of the projects has also been stressed.

    Up to now, he said, the number of Olympic venues and related projects under construction has reached 45, including 25 competition venues, 15 training venues and 5 Olympic-related projects. In addition, Fengtai Softball Field (a renovated project) and the track field of Chaoyang Sports Center (a training venue) are ready for use. Updating on the venues to be constructed from scratch, Wu said:

    Related readings:
    Beijing 2008 posters get attention at Doha Games
    Paralympics volunteers in action
    Beijing residents have highest monthly income
    Beijing to continue renovating scenic parks
    Roof-gardens to boost Beijing Olympic development drive
    Solar power to heat water for athletes
    Beijing plans new emission standard for vehicles

    With the successful welding of the main steel structures on August 31, the removal of the supporting steel beams on September 17 and the hoisting work of the steel structure on November 30, the construction on the National Stadium's main structure has been fully completed. Construction of the main stadium, also called the "Bird's Nest," is shifting to the installation of membranes, fit-ups and decorations, installation of electromechanical equipment and the exterior engineering project.

    -- The National Aquatics Center: The main steel structures have been completed, the installation of the membrane structure is in smooth progress, and construction on the walls and the installation of the membrane structure of the outside roof are expected to be finished by the end of this year.

    -- The National Indoor Stadium: Work on the main structure and steel structure has been finished, the steel roof and exterior decoration are scheduled to be done by the end of this year.

    -- Wukesong Indoor Stadium: Steel structure completed, installation of the roof and curtain walls in well underway, and the exterior decoration is expected to be completed by the end of this year.

    -- China Agriculture University Gymnasium, Beijing University of Technology Gymnasium, Peking University Gymnasium and the Beijing Science and Technology University Gymnasium: Steel-reinforced concrete structure and steel structure completed, the metal roof and curtain walls under construction.

    -- Shunyi Olympic Rowing-Canoeing Park: Excavation of the racing courses finished, the key steps shifted to the water reservation and experimentation, with other separate project under construction or decoration.

    -- Beijing Shooting Range Hall: Interior decoration is being done.

    -- Laoshan Velodrome: Decoration and installation of equipments underway.

    -- The Olympic Green Tennis Center: Construction of concrete structure of the field is being done, and the main concrete structure is planned to be completed by the end of this year.

    Turning to the projects under renovation and expansion, Wu said:

    -- Fengtai Softball Field: Ready for use.

    -- Workers'Stadium and Workers' Indoor Arena: Dismantlement and reinforcement work in progress.

    -- Beijing Shooting Range Hall CTF: Construction on the main body, pit and range infrastructure underway.

    -- The Olympic Sports Center Stadium, Olympic Sports Center Gymnasium, Ying Tung Natatorium and Capital Indoor Stadium: Structural reinforcement and expansion of the existing venues in progress

    -- Laoshan Mountain Bike Course: Structural construction of the Complex Service Building completed.

    -- Beihang University Gymnasium and Beijing Institute of Technology Gymnasium: Renovation and expansion being prepared and expected to be launched by the end of December 2006.

       Previous   1,   2,   Next  
    Comments of the article(total ) Print This Article E-mail
    PHOTO GALLERY
    PHOTO COUNTDOWN
    MOST VIEWED
    OLYMPIAN DATABASE
    日本中文字幕中出在线| 无码人妻少妇久久中文字幕蜜桃 | 国产亚洲?V无码?V男人的天堂| 中文字幕无码久久精品青草| 亚洲天堂2017无码中文| 人妻少妇精品无码专区二区 | 亚洲AV无码欧洲AV无码网站 | 亚洲中文字幕无码不卡电影| 今天免费中文字幕视频| 无码精品人妻一区| 国产在线精品无码二区| 亚洲AV无码精品色午夜果冻不卡| 久草中文在线观看| 成人精品一区二区三区中文字幕 | 日本妇人成熟免费中文字幕 | 亚洲AV无码一区二区一二区| 人妻无码久久一区二区三区免费| 中文字幕av无码一区二区三区电影 | 八戒理论片午影院无码爱恋| 91天日语中文字幕在线观看| 无码专区中文字幕无码| 99在线精品国自产拍中文字幕| 无码人妻一区二区三区精品视频 | 亚洲无码日韩精品第一页| 国产精品一级毛片无码视频| 精品无码久久久久久午夜| 日韩精品久久无码中文字幕| 手机永久无码国产AV毛片| 亚洲AV无码国产精品色午友在线| 亚洲AV无码国产精品色午友在线 | 亚洲va中文字幕无码久久不卡| 亚洲真人无码永久在线| 亚洲AV无码一区二区三区性色| 亚洲av永久无码精品网站 | 成人av片无码免费天天看| 本道天堂成在人线av无码免费| 东京热加勒比无码视频| 无码AV大香线蕉| 无码专区中文字幕无码| 亚洲精品一级无码中文字幕 | 小13箩利洗澡无码视频网站|