    Rising to a tunnel's challenge

    By China Daily | China Daily | Updated: 2017-06-09 07:32

    Rising to a tunnel's challenge

    Workers deal with gushing water during the construction of the Dazhushan Tunnel on the Dali-Ruili Railway project in May.Provided To China Daily

    When work began on the Dazhushan Tunnel, the plan was to finish it in five years. That was in 2008 - and construction crews are still digging.

    Unexpected difficulties mean the 14.5-kilometer tunnel, a critical juncture on the Dali-Ruili Railway in Yunnan province, is now scheduled for completion in 2021, Xinhua News Agency reported.

    The tunnel runs through six faults in the Hengduan Mountains on the Qinghai-Tibet Plateau. It would have been beyond imagination to build on the earth fractures 20 years ago, said You Hongsheng, a spokesman for No 4 Company of China Railway First Group Co, which is digging the tunnel.

    Rising to a tunnel's challenge

    In August 2009, immediately after the first drilling began at one of the six fault lines, a 20-centimeter crack appeared in the operating face. The crack continued to widen as mudrock gushed out, filling a space 200 meters long and 6 meters high in about five hours.

    "We failed to predict the fragility of the fault," said Jiang Dong, a construction manager at the site. "It is just like drilling into a piece of bean curd. The mudrock started to flow into the tunnel as we worked."

    Jiang said the problem was later solved by building a wall to stop the mudrock flow and grouting the flow until it became solid. "Then we dug through the solid part to carry on with the project."

    Rising to a tunnel's challenge

    ?

    An estimated 140 million cubic meters of water have been pumped out of the tunnel over the past nine years of construction work.

    In addition to the day-to-day operating challenges, the geologic complexity of the area where the tunnel is located has made working conditions extremely tough for workers.

    In most parts of the construction site, it's quite humid, with the temperature in the hole at around 37 C. Workers had to alternate in two-hour shifts to continue through the day.

    Some workers have left the project because of the rough working conditions and the extended construction time. Others, however, stayed put and were determined to hold their ground until the tunnel's completion.

    Jiang said when he began working at the site his daughter was in second grade, and now she is in senior high school. He has been able to be home for just 20 days every year.

    Wu Hao, 25, chose to stay with the project even though his father needed him in the family business.

    "I need to prove myself in this project. How can I give up halfway?" Wu said.

    When the Dali-Ruili Railway is complete, it will take a train just five minutes to run through the tunnel. Few passengers will know that it took 13 years to build.

     

    Editor's picks
    Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
    License for publishing multimedia online 0108263

    Registration Number: 130349
    FOLLOW US
     
    免费无码一区二区三区蜜桃| 亚洲av综合avav中文| 影院无码人妻精品一区二区 | 人妻无码中文久久久久专区| 久久国产精品无码HDAV| 日本久久久久久中文字幕| 久久伊人中文无码| 精品无码AV无码免费专区| 中文字幕有码无码AV| 爆操夜夜操天天操中文| 亚洲AV无码成H人在线观看| 国产精品无码久久综合| 无码人妻黑人中文字幕| 人妻少妇无码精品视频区| 中文字幕欧美日韩在线不卡| 中文字幕av高清片| A级毛片无码久久精品免费| 无码GOGO大胆啪啪艺术| 中文无码伦av中文字幕| 高清无码中文字幕在线观看视频| 精品久久久久中文字幕日本| 欧美乱人伦中文字幕在线| 精品久久久久久无码免费| AV无码免费永久在线观看| 无码丰满少妇2在线观看| 无码国产精成人午夜视频一区二区 | 亚洲人成人无码网www电影首页| 无码国内精品久久综合88| 中文无码喷潮在线播放| 精选观看中文字幕高清无码| 中文字幕免费高清视频| 天堂在线观看中文字幕| 中文字幕在线免费看线人| 中文字幕无码不卡免费视频 | 亚洲国产成人片在线观看无码| 人妻丰满熟妇AV无码区HD| 国模无码人体一区二区| 中文有无人妻vs无码人妻激烈 | 国产精品无码v在线观看| 日韩美无码五月天| 日本阿v视频高清在线中文|