Japan disaster plant's cold shutdown could face delay

    Updated: 2011-08-18 08:16

    (China Daily)

      Comments() Print Mail Large Medium  Small 分享按鈕 0

    TOKYO - Tokyo Electric Power Co (TEPCO) said on Wednesday that it may fail in its bid to achieve "cold shutdown" at its tsunami-hit nuclear plant in Fukushima by January, as the world's worst nuclear crisis in 25 years rumbles on.

    Efforts to decontaminate highly radioactive water at the facility have been delayed by repeated breakdowns of cesium absorption instruments, which have caused water leakage and malfunctioning of pumps, threatening to delay the process of stabilizing the stricken plant.

    "It's possible that decontamination may not be completed as planned by the year-end, although we have not yet decided to change the target. That could affect the cold shutdown process," a company spokesman said.

    His comments follow a similar statement on Tuesday, reported in the Nikkei business daily, from Junichi Matsumoto, a TEPCO spokesperson on nuclear issues.

    Cold shutdown is usually defined as meaning the water in a reactor is below 100 C at normal atmospheric pressure, making its radioactive fuel safe from heating up again.

    TEPCO also confirmed on Wednesday that it is testing a new radioactive water processing instrument as it struggles to cope with the damage wreaked by the 9.0-magnitude earthquake and tsunami that devastated the country's northeast coast in March.

    With only an estimated 42,000 tons of highly contaminated water having been processed by Aug 9, roughly 120,000 tons are still left in the basement in turbine buildings and elsewhere.

    TEPCO had set a goal of processing 200,000 tons of radioactive water by year-end since more water will be contaminated in the process of bringing the damaged reactors under control.

    TEPCO officials and nuclear crisis minister Goshi Hosono were scheduled to hold a joint news conference on Wednesday to explain progress on work to bring the damaged reactors under control.

    The test run of Toshiba Corp's cesium adsorption instrument, known as Sarry, is being carried out by running water with low-level radiation through equipment from French nuclear firm Areva SA and US nuclear waste management company Kurion Inc. It is scheduled to start operating fully as early as Thursday, Tepco officials said.

    Sarry is relatively easy to maintain because it has fewer pumps, the breakdown of which have been a major reason for delays. Even if the system's overall operating rate holds steady at 90 percent, roughly 195,000 tons will be processed this year.

    Reuters

    Hot Topics

    The European Central Bank (ECB) held a conference call late on Sunday ahead of the market opening, pledging the ECB will step in to buy eurozone bonds with efforts to forestall the euro zone's debt crisis from spreading.

    亚洲av无码一区二区三区四区| 日本中文字幕在线不卡高清| 欧美中文字幕一区二区三区| 亚洲AV区无码字幕中文色| 香蕉伊蕉伊中文视频在线| 国产AV无码专区亚汌A√| 成年无码av片完整版| 亚洲日韩v无码中文字幕 | 中文字幕精品久久| 中文字幕无码日韩专区| 变态SM天堂无码专区| 亚洲精品无码久久久久久| 久久五月精品中文字幕| 中文字幕久精品免费视频| 日韩精品无码免费视频| 精品无码人妻夜人多侵犯18| 成人无码AV一区二区| 精品人妻系列无码一区二区三区| 亚欧成人中文字幕一区| 亚洲精品无码99在线观看| 国产精品一区二区久久精品无码| 无码人妻丰满熟妇精品区| 亚洲AV无码一区二区三区性色 | 成人午夜亚洲精品无码网站| 久久久99精品成人片中文字幕 | 免费无码一区二区三区蜜桃| www.中文字幕| 日韩中文字幕在线播放| 亚洲av中文无码乱人伦在线播放| 中文字幕精品无码一区二区三区| 中文字幕亚洲欧美专区| 精品人妻中文av一区二区三区| 中文字幕网伦射乱中文| 天堂网www中文在线| 亚洲人成中文字幕在线观看| 熟妇人妻久久中文字幕| 日韩中文字幕在线| 区三区激情福利综合中文字幕在线一区亚洲视频1 | 天堂а√在线中文在线| 亚洲一区二区中文| 最近中文字幕免费mv在线视频|